Planning matters

Our award winning blog gives a fresh perspective on the latest trends in planning and development.

Does the Wales Infrastructure Act Risk Slowing Battery Storage Delivery?

Does the Wales Infrastructure Act Risk Slowing Battery Storage Delivery?

Arwel Evans 24 Nov 2025
The infrastructure consenting process will take effect on 15 December 2025 (subject to transitionary arrangements), introducing a new consenting framework for nationally significant infrastructure projects (SIP) in Wales, replacing a number of existing consenting regimes including DNS. While the legislation aims to streamline the consenting of complex projects, its treatment of Battery Energy Storage Systems (BESS) raises important questions about proportionality, efficiency, and Wales’ ability to deliver the flexible energy infrastructure required to achieve its climate ambitions.
Under the Act, BESS schemes between 50MW and 350MW will fall within the new Infrastructure Consent regime, determined by Welsh Ministers and requiring an Infrastructure Consent Order. Smaller and larger schemes will remain with the Local Planning Authority (LPA) under the existing Town and Country Planning Act (TCPA) process. This banded approach has created an unexpected anomaly, with implications for both developers and decision-makers.

 

A New Consenting Threshold – and an Anomaly
Unlike the NSIP framework in England and the DNS regime in Wales (that is to be replaced) - the Infrastructure Act does not carve out BESS from national-level consenting. Welsh Government has confirmed that BESS is captured as a “generating station” under Section 2 of the Act.
 
This results in the following consenting structure:
 
Scale of BESS
 
Consenting Regime
 
 Determining Authority
 
  < 50 MW   TCPA   Local Planning Authority  
  50-350 MW   Infrastructure Consent    Welsh Ministers  
  >350 MW   TCPA   Local Planning Authority  
 
It is unclear if the above consenting structure is intentional or whether it is a drafting anomaly that does not reflect wider policy intent.
 
Implications for Delivery
Placing 50–350MW BESS projects into a national consenting framework will likely introduce longer determination times, higher preparation costs, and increased pressure on PEDW and Welsh Minister’s consenting capacity.
 
Given that many BESS schemes fall within this capacity range, the shift could influence the number and pace of applications coming forward. Wales may find itself at a competitive disadvantage compared with England, where all BESS—regardless of scale—are determined by LPAs. It may be that developers will choose to apply for schemes greater than 350MW in order to bypass the SIP process.
 
With Senedd Cymru elections scheduled for May 2026, the window for legislative amendment before commencement is extremely narrow, even if the administration were minded to revise the approach.
 
Context: A Divergent UK Policy Landscape
The consenting of BESS projects differs across the UK:
 
Country
 
Consenting approach for BESS
 
  England   Since 2020, all BESS (except pumped storage hydro) has been removed from the NSIP regime regardless of size. The UK Government concluded that the time and cost associated with NSIPs was not proportionate to the planning impacts of modern storage technologies.  
  Scotland   BESS over 50MW requires consent from Scottish Ministers, reflecting a more centralised approach.  
  Wales   From 15th December onwards the consenting of BESS between 50MW and 350MW will be determined via the SIP process.  
Such divergence risks creating uncertainty for developers operating across borders and may undermine wider public understanding of how these projects are assessed.
 
 
BESS and the Energy Transition
Battery storage plays a central role in achieving a low-carbon, resilient electricity system. By storing electricity when renewable generation is plentiful and releasing it during periods of high demand, BESS provides:
  • essential grid balancing,
  • frequency response and stability, and
  • support for the wider transition away from fossil fuels. 
National Grid has described BESS as “essential to speeding up the replacement of fossil fuels with renewable energy”. Any consenting approach that delays deployment risks limiting Wales’ ability to transition to net zero by 2035[1].
 
 
Should BESS Be Treated Like Large-Scale Generation?
BESS is critical infrastructure necessary in the move to net zero, but its impacts differ significantly from large-scale renewable generation such as wind or solar. BESS projects do not normally require associated consents or CPO powers which the Infrastructure Consent process is geared up to provide and, in some cases, do not require EIA. While issues such as fire safety have been raised in certain contexts, these matters are well-established within the TCPA process and are routinely managed through appropriate assessment and conditions. For example, in October 2024 Cardiff Council granted permission for a 1GW BESS project in Splott[2].
 
Given recent efforts by both UK and Welsh Governments to simplify consenting for energy storage, its re-inclusion in a national regime represents a notable policy shift. This appears misaligned with established planning policy.
 
 
Planning Policy Position
Wales’ national planning framework strongly supports the deployment of energy storage:
  • Future Wales: The National Plan 2040 notes the need to integrate large-scale energy storage to ensure grid balancing (supporting text to policy 18).
  • Planning Policy Wales emphasises the role of storage in managing the intermittency of renewable generation and states that proposals should be supported wherever possible (paragraph 5.7.12).
These statements underline the strategic importance of BESS—yet the Infrastructure Act may introduce barriers that could slow delivery.

 

The Pros and Cons of each route
     
Pros
 
 Cons
 
 
TCPA
 
  • Local control over the sitting and design of proposals. 
  • Retention of planning fees at a local level, supporting stretched planning budgets.
  • Quicker decisions
 
  • Potential for lack of consistency between different authorities. 
  • Resource pressure of large workloads. 
 
 
Infrastructure Consent
 
  • Process and outcome should be more certain. 
  • Removes local politics from the decision-making process. 
  • Decision made having regard to Future Wales and any infrastructure policy statement that has an effect.  
 
  • Larger application costs including application fees and consultant/legal costs involved in examination and drafting of the order. 
  • Longer determination timescales. 
  • Disproportinate for this type of project. 
 
 
Part 5 of The Act notes that decisions by Welsh Ministers can have regard to infrastructure policy statements and in our view that could give more certainty to developers pursuing BESS applications via SIP. However, we understand that Welsh Government are unlikely to bring forward such infrastructure policy statements and will rely on Future Wales for the time being, potentially undermining the benefit of the national consenting regime.
 
 
Conclusion
The Wales Infrastructure Act offers an opportunity to modernise and streamline the consenting of major infrastructure and for complex projects it will probably be successful in doing so. However, the inclusion of BESS schemes between 50MW and 350MW within the new Infrastructure Consent regime raises concerns about proportionality and deliverability. Whilst there are clear merits to the new regime for more complex projects,  a more balanced approach—mirroring recent steps taken in England—may better support Welsh Government’s own policy objectives around flexibility, resilience, and decarbonisation. As the Act moves towards implementation, clarification or refinement of BESS thresholds could help ensure that Wales remains an attractive and efficient location for the deployment of this essential technology.
 
Lichfields has secured planning permission for numerous BESS projects across the UK including several in Wales. Feel free to contact Arwel Evans to discuss any future projects that may be affected by the new consenting regime.
 
 
Footnotes
[1] This is one of the commitments in the Cooperation Agreement between the Welsh Government and Plaid Cymru following the elections in May 2021.