The refusal of the Botley West Solar Farm is a useful reminder that the Government’s drive for net zero and to deliver renewable energy at pace does not make other infrastructure constraints disappear. 
On 10 November 2026, the Secretary of State  (SoS) refused development consent for the 840 MW scheme of solar arrays across 839Ha of land.[1] The decision accepted the Examining Authority’s (ExA) recommendation to refuse consent, following the development consent order (DCO) examination.[2]
The decision was big news.[3] The headlines focused on harm that would be caused to Green Belt and heritage assets, as well as negative impacts on the landscape. But for solar developers working around airports, another part of the decision deserves particular attention.
Aviation safety was not a side issue. It was one of the matters given substantial negative weight in the planning balance. That is striking for a project whose need case was itself afforded substantial positive weight. Aviation safety was discussed extensively in both the decision letter and the ExA report.
The concerns centred largely on London Oxford Airport. The proposed Botley West Solar Farm was not simply in the wider vicinity of London Oxford Airport: parts of the solar array extended into the immediate operational environment of the aerodrome.
In particular, panels were proposed within areas identified by the airport’s Local Runway Safety Team as potentially required for emergency landing following an engine failure after take-off, with the Examining Authority noting a “considerable bank” of panels between the runway and nearby woodland even after approximately 50 hectares of proposed panels were removed during the examination.
Ultimately, the decision-makers concluded that the development could affect public safety, the security and viability of the solar farm’s own operations, and the airport’s operations and contribution to the local economy.
That does not translate into a blanket rule against solar near airfields. Solar arrays can, and do, coexist with aviation. The more useful lesson from Botley West is about when aviation constraints are understood, how they influence site selection and design, and whether mitigation is built into the scheme or bolted on later.
  1. Start with the airport, not the mitigation: Early, meaningful engagement with the airport and other neighbours is critical, and it needs to shape the scheme not amend it. At Botley West, the  ExA considered that critical information from the airport had been overlooked or ignored, leading to misunderstandings about operation effects. Aviation mitigation was consequently underdeveloped. An aerodrome is not just another consultee to be dealt with once the layout has largely crystallised.

  2. Understand how the aerodrome actually works: A runway on a plan tells only part of the story, and no two airports are the same. Flight approaches, circuit patterns, training activity, aircraft types, emergency procedures, radar and air traffic control all matter. So does the Airport’s commercial model. The assessment must start with the particular aerodrome, rather than a generic assumption about what airport safeguarding requires.

  3. Treat aviation safety as a design input:

    Obstacle limitation surfaces (OLS): establish at the outset whether any part of the development could breach these safeguarded surfaces and what that means operationally.

    Engine failure after take-off (EFATO): identify the land pilots may need in an emergency, particularly where training aircraft and inexperienced pilots are involved. How would the location of the solar array affect those areas?

    Glint and glare: assess real flight operations, not simply the runway centre-line. Visual circuits, approaches, departures and air traffic control may expose pilots and controllers to reflections in different ways.

    Turbulence: consider how heat from extensive solar arrays might affect airflow around the airport and radar performance. Botley West is particularly notable because the Secretary of State treated this as an emerging technical field and applied a precautionary approach.

    Bird strike: consider the scheme and its ecological mitigation together. Habitat creation or planting that is beneficial in one respect, can alter bird activity and create a different aviation risk.

  4. Do not separate safety from the airport’s economics: The decision also recognised the potential knock-on effect on the airport’s economic viability if flight-training operators concluded that they could no longer operate safely. At London Oxford Airport, flying schools account for around 80% of aircraft movements. Understanding the users of an aerodrome, and the consequences if their operations are constrained, is part of understanding the planning impact.

  5. The wider lesson is one of front-loading. The Overarching National Policy Statement for Energy (NPS EN-1) (2024) requires applicants of all types of energy infrastructure development to minimise adverse effects on aerodrome operations and safety, and the Botley West decision shows the risk of leaving that work until the examination or post-consent stages. The Secretary of State’s criticism repeatedly returns to the same theme: baseline understanding, scheme design and mitigation need to follow in that order.
For solar developers (and indeed developers of all energy infrastructure), that means testing aviation constraints before the red line and panel layout become difficult to change. For airport operators, it means getting operational and commercial evidence into the process early enough to influence design, rather than simply object to it afterwards.
Lichfields represented Oxford Aviation Services Limited (London Oxford Airport) during the examination. If you are a solar developer considering a scheme near an aerodrome, or an airport faced with one, please get in touch.

 