Planning matters

Our award winning blog gives a fresh perspective on the latest trends in planning and development.

Make more little Plans? The NPPF’s shift to ten-year local plan periods

Make more little Plans? The NPPF’s shift to ten-year local plan periods

Matthew Spry 27 Aug 2026
The Chicago urbanist Daniel Burnham made this famous injunction to planners:
"Make no little plans; they have no magic to stir men's blood."[1]
It creates a slightly awkward contrast with one part of the first planning policy issued under his Prime Ministerial namesake. The August 2026 National Planning Policy Framework (NPPF) reduces the minimum local plan horizon from 15 years to “no less than 10 years from the point of adoption.”[2]

The change most respondents didn’t ask for

 

The December 2025 draft did not start here. Draft Policy PM2 proposed retaining the 15-year horizon. It was the accompanying consultation that asked whether this should instead be ten years.[3]
The Government response records 1,074 responses to Question 10a. 69% disagreed with reducing the period to ten years. The response summarised the main concerns: that a shorter horizon would undermine long-term planning and create difficulty for larger strategic sites. The Government nevertheless proceeded, citing the new 30-month timetable, the expectation that plans are commenced no later than five years after adoption, and the role of Spatial Development Strategies (SDSs) in setting a longer strategic framework.[4]
Of course, it is for Government’s to decide: a consultation is not a referendum. But it does mean the shift should be seen for what it is: a deliberate choice rather than a product of consensus.

 

Back to the Future?

 

As ever, there is a historical benchmark.
PPG12 (1999) advised that the duration of local plans should normally extend for ten years from forecast adoption date.[5]
Back then - as now intended with SDSs - a local plan did not carry the strategic burden. In two-tier areas, the Structure Plan provided a county-wide framework. The local plan translated that into detailed allocations and policies. Above it was Regional Planning Guidance (RPG).
The 2004 reforms replaced RPG and Structure Plans with statutory Regional Spatial Strategies (RSSs). The 2004 update of PPS12 maintained the ten-year horizon, but with the aim to look ahead for the longer-term, set by RSS.[6]
So, is the case for moving back to ten years properly explained simply with reference to reintroduction of a strategic planning tier? Only up to a point.
The move to minimum 15-year period from adoption period for local plans actually came in the 2008 version of PPS12, when the then-Government’s vision for strategic planning was at its zenith.[7]
This was then carried through into the localism era; to the 2012 NPPF where a 15-year horizon was a ‘preference’.[8]  Later NPPF editions converted this into a firmer ‘minimum’,[9] with a vision for longer periods (of up to 30 years) expected where plans included larger-scale development.[10]
The new shift to ten years is therefore a genuine reversal in approach, even if it revives a duration from a previous planning generation.

 

Why the effective plan period will be much shorter than ten years

 

Even if the nominal period for the plan is ten years from adoption, the period for which its new proposals can influence housing delivery is shorter, perhaps just half its period. This comes down to lead-in times and the inescapable facts of a trajectory.
Under Policy HO3, plans need to demonstrate a five year land supply of “specific deliverable sites” at adoption and developable sites for years six to ten.
Most of the supply treated as deliverable in years 1–5 will come from the inherited planning and development pipeline.[11]
A plan’s new proposals focus more on shaping supply in years 6–10 and beyond, as   developable sites and broad locations come forward following applications prepared in the first phase.  The window in which new allocations can move through consent and into delivery has been heavily concentrated from years six onwards.
A shorter plan period, might not matter if development was getting faster. The evidence points the other way.
Lichfields research - How long is a piece of string? - found that the average time taken to determine a major outline residential application had risen from eight months in 2014 to two years in 2024.[12]

Strategic sites: less reward for the same difficulty

 

The analysis in Start to Finish shows that for large strategic sites of 1,500 homes or more - the threshold the NPPF itself now uses to define one[13] - the planning and pre-commencement periods can run well beyond five years before a single home completes.[14] All things being equal, the strategic sites the NPPF now encourages (via Policy HO4) will contribute relatively little or nothing within the ten-year period against which the plan is tested.[15]
Strategic sites require the most difficult choices about the distribution of growth, settlement form, infrastructure funding, transport, landscape, Green Belt, education, health, utilities, viability and community impact. They are also most politically visible. The costs, controversy and technical work are front-loaded. A shorter plan period does not make any of these issues any easier. It simply reduces the proportion of the site’s eventual output that helps the plan meet its requirement. This changes the calculus for difficult choices and trade-offs – see Table 1. It is ironic[16] that the NPPF’s positive framework for strategic sites is accompanied by a measure that makes local planning authorities (LPAs) less incentivised to allocate them.
 

Table 1 Fifteen year and ten-year plan horizons: different incentives

Issue
15-year plan horizon
10-year plan horizon
New strategic allocations  More later-year delivery can count toward the plan period.  Earlier years dominate the development trajectory. 
Infrastructure planning  More scope to plan for strategic infrastructure and phased delivery.  Greater temptation to rely on infrastructure already in the pipeline or capable of near-term delivery. 
Political incentives  Difficult choices are harder to defer because more need must be planned for.  More difficult or strategic choices can be pushed into the next local plan. 
Housing supply resilience  More capacity to create a rolling pipeline beyond existing permissions and hedge against uncertainties associated with supply.  Greater dependence on existing commitments, windfalls and residual allocations.  

 

SDSs are the counterargument - but not a complete answer 

 

The Government’s consultation response points to the fact that local plans site alongside SDSs which will set a positive vision for growth at a sub-regional scale. The December 2025 draft suggested they plan for at least 20 years; the 2026 NPPF increased it to 25.
Policy PM2(1)(a)(iii) requires local plans to reflect longer-term expectations extending beyond the plan period where appropriate, including for large-scale development proposals.
That provides a hook for local plans to engage with large-scale development that will not make its full contribution within the 10-year local plan period. It gives examining Inspectors and strategic plan-makers the basis to ask whether a local plan is genuinely aligned with the longer-term picture rather than simply meeting the housing needs of the first decade (See NPPF Policy PM2(1)(a)(iii) and PM2(1)(b). But that leaves three practical challenges:
 
  1. Dependency on the SDS doing the hard yards of identifying broad locations for growth, rather than just distributing housing targets.  The history of some RSSs shows such plans can also be vulnerable to political deferral.[17] Will all Mayors and combined authorities be up to the challenge of setting broad locations rather than delegating the difficult choices to LPAs, who can then use a shorter plan period to duck them? 
     
  2. Secondly, timing matters. Many SDSs will need to be prepared through new as yet untested governance arrangements. That creates uncertainty over sequencing; if the new plan making system is as effective as promised, many new-style local plans are likely to be well down the track before the SDS has laced its boots. 
     
  3. Thirdly, SDSs do not allocate specific sites or scrutinise deliverability in the way local plans do.[18] Experience suggests that LPAs ambivalent about growth can be adept at deferring the difficult question (for, example, an SDS broad location where the local evidence suggests barriers to implementation) to the next local plan cycle. They may have in mind a hope for a change in political weather that will see the SDS revoked or changed in the meantime.
     
Strategic planning is essential, but it is not magic; nor is its effectiveness automatic. It will need governance, evidence, discipline, scrutiny and diligent examining inspectors.
Ultimately, there is little evidence that 15-year local plans were an obstacle to strategic planning. Indeed, the 2008 PPS12 shift to 15-year plans suggests they are (were) an enabler of its effectiveness. 

 

What problem is the ten-year plan designed to solve?

 

There is a legitimate concern that local plans have been too complex, take too long to prepare, and often failed to stay up to date. But it does not follow that a 15-year horizon was the cause. The evidence points to a broader set of problems: policy churn, resourcing constraints, statutory consultee delay and political risk.[19] 
That being the case, the solutions are to simplify process, reduce duplication, improve evidence proportionality, align infrastructure bodies, maintain clear national policy and properly resource plan-making. That is what the LURA and new NPPF reforms have been about.[20] 
Does a shorter period, thus with less housing to provide for, mean the local plan strategy easier to prepare? Counterintuitively, the answer is no; it may even make it more difficult. A study of most housing supply trajectories explains why. They typically show a total supply broadly equal to the plan’s total housing requirement (its target) with the delivery of pipeline supply in years 1-5, a bulge of developable sites for years 6-10 before it falls away in years 11-15.[21] Real world delivery is then spread out, some sites proceeding as planned, others taking longer.[22] Reduce the plan horizon to ten years and you concentrate the risk associated with delivery in years 6-10 onto a smaller pool of sites. This demands better evidence on deliverability or to allocate more land than the total housing requirement to act as a buffer.
The shorter horizon thus sits a little awkwardly with the Minister of State’s recent letter on pragmatism in local plan examinations.[23] The letter urges inspectors to assess allocations over the plan period as a whole and to distinguish fundamental barriers from matters that “could reasonably be expected to evolve over time as market conditions change”. Its central proposition depends on there being sufficient time for circumstances to evolve; ten years gives less of it.[24]
The change to ten year plans does not itself simplify; it just reduces how much future growth the plan must address. If a barrier to plan making was that they involve difficult choices over planning for growth, it is an curious response for a growth-orientated government to say the answer lies in asking them to do less.

 

More little plans? 

 

Most of the policies in the new Framework seem likely to support the achievement of the Government’s ambitions for housing growth, but the shift to ten-year local plans is a material wrinkle. 
The change was not asked for and the case for it is not proven. There are arguments to support how it might work that are coherent in theory.[25] But only if every plan maker behaves how the Government wants them to.
But history tells us not all participants in plan making do what Government expects, and minimum requirements shape behaviour. And any political instability at local, mayoral and national levels will make it more likely plan making is gamed or decisions are ducked, with growth falling between the cracks. The case for sticking to 15 years was (and is) unassailable.
Daniel Burnham’s maxim was not arguing for big plans at any cost. It was an argument for plans with enough ambition and permanence to shape the future. More frequent plans may be welcome, but if each local plan is encouraged to look only just far enough ahead to avoid the toughest choices, the system may produce more plans while doing less effective planning.

 

Footnotes

 

[1]  Those interested in diving down rabbit holes can trace the etymology of that particular quotation here. The full quote, which came as the peroration of a longer speech, was: “Make no little plans; they have no magic to stir mens’ blood and probably themselves will not be realized. Make big plans; aim high in hope and work, remembering that a noble, logical diagram once recorded will never die, but long after we are gone will be a living thing, asserting itself with ever-growing insistency. Remember that our sons and grandsons are going to do things that would stagger us. Let your watchword be order and your beacon beauty.”
[2] Policy PM2(1)(b) of the new Framework says the local plan should set “out a spatial strategy, policies for the minimum amount of development to be provided, land allocations and broad locations for growth, and designations in accordance with policy S2, for a period of no less than 10 years from the point of adoption of the plan."
[5] ODPM, Planning Policy Guidance Note 12, 1999, para 6.8. It also applied to Part II of Unitary Development Plans.
[6] Para 2.14 of PPS12 stated: “The local planning authority should ensure that policies and proposals in the core strategy provide certainty for the future. The time horizon of the core strategy should be for a period of at least 10 years from the date of adoption. However the core strategy should aim to look ahead to any longer-term time horizon which is set out in the relevant regional spatial strategy. The core strategy should be kept under review and the horizon rolled forward in subsequent reviews of the document.”
[8] MHCLG, NPPF, March 2012
[9] MHCLG, NPPF, July 2018
[10] DLUHC, NPPF, July 2021. The 30-year horizon was a response to issues raised in my blog on the failure of several new settlements in North Essex
[11] Sites under construction, benefiting from permission, subject to advanced applications or otherwise supported by clear evidence of near-term delivery.
[12] That is before taking into account the time beforehand preparing an application or the time afterwards discharging conditions, securing detailed approvals and resolving technical matters.
[13] NPPF, Annex B, defines a ‘Strategic site’ as “typically… at least 1,500 dwellings” for residential-led
development
[14] Larger sites' planning and pre-commencement periods extend well beyond five years from first application.
[15] Policy HO4 states that Local plans should “where appropriate, identify suitable locations for strategic sites for housing-led development (such as new settlements, new urban quarters or significant extensions to existing settlements).”
[16] At risk of falling into the trap that befell Alanis Morrisette
[18] The test of effectiveness for SDS (PM14) is “and there is a reasonable prospect that local plans will be capable of identifying site allocations to implement its spatial strategy. Where spatial development strategies anticipate a change in market conditions which the strategy itself is intended to foster, a proportionate approach should be taken in assessing assumptions for the longer term, given the uncertainty which is likely to surround them.” For Local plans (PM15) it is: “the plan sets out effective policies for development, and there is a reasonable prospect that its site allocations are capable of being deliverable at the time envisioned.”
[19] See for example, the 2016 report of the Local plans Expert Group, to which the author of this blog was an inconsequential contributor
[20] As explained in this MHCLG Blog from December 2025. The NPPF policy statement says the reform will: “make development management more certain, consistent and streamlined; standardise policies that apply across the whole of England; reduce duplication and avoid unjustified local deviation from national policy in local plans.”
[21] The housing trajectory in the recently adopted Winchester local plan is an exemplar of this pattern – see page 220.
[22] Reflecting optimism bias in the assessment of sites; most developable sites are expected by their promoters (and the LPA) to come forward at the earliest opportunity. See this article in Nature – previously cited in my blog on land value capture. Its review of behavioural research on real‑estate investment finds that developers are subject to persistent optimism bias, overconfidence, anchoring and confirmation bias, leading them to overestimate their own ability to deliver while underestimating costs, risks and constraints. See also the analysis by Homes England on Optimism Bias
[24] Sites in local plans are required to be deliverable or developable and where expected to contribute in years 6–10 “with a reasonable prospect that they will be available and could be viably developed at the point envisaged”. Decisive decisions over investment need to be made much earlier: land and infrastructure agreements, preparation of applications, utility commitments and funding decisions will likely need to be made in years 1–5. The shorter the plan horizon, the less room there is for a presently marginal but strategically important site to become deliverable by the time its contribution is required. A ten-year plan period does not give a site ten years for viability to recover.
[25] For example: The ten year period doesn’t stop local plans looking beyond ten years and they can – as now – allocate sites beyond the plan period. The NPPF has new encouragement to identify strategic sites of 1,500+ homes. If an SDS looking 25 years ahead identifies a broad location for long term growth in a plan area, then a local plan ought to have policies to facilitate it. Replacement local plans must commence within five years and new plan making intends them to be done quickly. It might be said that what a little plan doesn’t plan for this time, its rapidly produced successor can pick up next time round.

Categories